MMHE wins Bokor Phase 3 platform contract

Malaysia Marine and Heavy Engineering has been awarded an engineering, procurement, construction, installation and commissioning of central processing platform (CPP) for Petronas' Bokor Phase 3 re-development, offshore Malaysia.

The first steel cut is expected to be in Q3 2018 and the project is scheduled to be completed in mid-Q2 2020. On completion, the new CPP will be installed at Bokor field, in Baram Delta, offshore Sarawak, in 70m water depth.