FPSO Compressor Fault Affects Pharos' Vietnam Output. Infill Drilling Campaign Complete

Armada TGT-1 FPSO - Image Credit: Pharos Energy
Armada TGT-1 FPSO - Image Credit: Pharos Energy

Pharos Energy plc, an oil and gas exploration and production company, with an interest in the TGT field offshore Vietnam, has completed the first phase of the infill development drilling program at the field, however, it has also experienced a setback with an FPSO compressor.

The Hoang Long Joint Operating Company (HLJOC), in which Pharos holds a share, has brought all four wells online, as part of the first phase of the infill drilling campaign. The second phase will include two more wells which are planned to be drilled in the third quarter of 2022.

According to Pharos, the initial flow of the four development wells of 8,800 bopd exceeded the predicted combined initial oil rate of 5,650 bopd by 3,150 bopd.
Also, Pharos said that well interventions and a gas lift optimization program earlier in the year resulted in an initial TGT production gain of 3,200 bopd. 

The six wells with additional perforations showed a gain of 1,800 bopd, the four wells with water shut off gained 900 bopd and eight wells where demulsifier injection was applied gained 500 bopd.

Compressor fault

Pharos said that the GTC-A compressor, one of the two compressors on the FPSO at the field, was stopped on Monday, November 15, to prevent any potential damage due to excessive temperature and vibration. 

The exact cause of the problem is under investigation but will require the compressor to be airfreighted to the manufacturer in the US for inspection and repairs. It is currently anticipated that the GTC-A will be back in service by end of January 2022," Pharos said.

The TGT field gross production rate on November 17, 2021, was 14,800 boepd, but would have been approximately 19,800 boepd without the impact of the compressor fault, as ~5,000 boepd is temporarily shut-in while Pharos Energy investigates the compressor fault.

"Our net production guidance of 5,500 - 6,000 boepd remains unchanged and we will keep the market updated on the progress of the compressor investigation," Pharos added.
 


Current News

Unique Group Celebrates 30 Years of Innovation

Unique Group Celebrates 30 Yea

Talos Energy Makes Leadership Team Changes

Talos Energy Makes Leadership

SOVs – Analyzing Current, Future Demand Drivers

SOVs – Analyzing Current, Futu

Equinor Cleared for Drilling Ops at Johan Castberg Field with Transocean Enabler Rig

Equinor Cleared for Drilling O

Subscribe for OE Digital E‑News

Offshore Engineer Magazine