First Dussafu DTM-4H Production Well Completed

Panoro Energy announced the successful completion of the DTM-4H well, the first of the phase 2 Tortue development wells, offshore Gabon.

The well was drilled with the Borr Norve jackup drilling rig in 116 meters water depth as a horizontal production well in the Gamba reservoir. A long horizontal section of good quality oil saturated Gamba sands was drilled and completed and the subsea tree installed ready for hook up early next year.

The rig has now moved to the DTM-5H well location, the second of the four phase 2 production wells, and the DTM-5H well was recently spud.

First production from the phase 2 Tortue wells is planned for March 2020 with all four phase 2 wells expected to be online by June 2020.

Current News

Hess Sets Date for Shareholder Vote on Chevron Merger

Hess Sets Date for Shareholder

US Releases Offshore Wind Liftoff Report and Promises Funding

US Releases Offshore Wind Lift

US Interior Department Finalizes Offshore Renewable Energy Rule

US Interior Department Finaliz

US Plans 12 Offshore Wind Auctions Over Five Years

US Plans 12 Offshore Wind Auct

Subscribe for OE Digital E‑News

Offshore Engineer Magazine