Albatros Topside Installed

Published

The topside for the Albatros substation has been installed in the German North Sea. (Photo: EnBW)
The topside for the Albatros substation has been installed in the German North Sea. (Photo: EnBW)

The topside of the offshore substation at the Albatros wind farm offshore Germany was installed Tuesday evening, developer EnBW said.

The heavy-lift jack-up vessel (HLJV) Pacific Ospray had loaded the topside in Rotterda, and once in the construction area, the HLJV Innovation lifted the topside on the foundation (monopile and transition piece) that had already been installed. 

The Pacific Ospray will be jacked up and remain next to substation until outstanding coating and welding work is completed.

Afterwards, the jack-up vessel Seafox2 will come to commission the offshore substation.

Current News

New Alliance Targets Offshore Caisson Integrity Challenges

New Alliance Targets Offshore

Mammoet Completes Record Module Loadout at Khalifa Port for Gas Project

Mammoet Completes Record Modul

Santos Prevails in Legal Challenge Over Climate Claims

Santos Prevails in Legal Chall

Trump Calls Out California, UK Energy Deal

Trump Calls Out California, UK

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine