Edvard Grieg Field Must Tap Land Power from 2022

Edvard Grieg (Photo: Lundin Petroleum)
Edvard Grieg (Photo: Lundin Petroleum)

Lundin Petroleum must redesign the electricity supply to its Edvard Grieg oilfield, in line with plans laid when the company won permission to develop the North Sea resource in 2012, the Norwegian energy ministry said on Friday.

Currently powered with gas turbines, the field's electricity should be supplied via power cable from land from 2022 onwards, coinciding with the startup of the second phase of the nearby Johan Sverdrup oilfield, which will also use land-based power.

The Sverdrup phase 1, Gina Krog and Ivar Aasen fields will also get power from land in a bid to cut emissions from the extraction of oil and gas.


(Reporting by Terje Solsvik, editing by Ole Petter Skonnord)

Current News

Cyprus Seeks Improvements to Chevron-led Plans for Offshore Gas Field

Cyprus Seeks Improvements to C

Equinor Seeks to Revive Costly Norway, Canada Oil Prospects

Equinor Seeks to Revive Costly

France Launches Call for 2.5 GW of Offshore Wind Tenders

France Launches Call for 2.5 G

ConocoPhillips Misses Quarterly Profit Estimates

ConocoPhillips Misses Quarterl

Subscribe for OE Digital E‑News

Offshore Engineer Magazine