Tanks installed on Caribbean FLNG project

Wison Offshore & Marine Ltd. (WOM) successfully completed the installation of the three LNG storage tanks into the hull of the Caribbean FLNG project. The project’s barge deck and topsides will now be installed.

The Caribbean FLNG project, supplied to EXMAR by Wison under an EPCIC contract, will be installed offshore Colombia.  The project started fabrication at the end of 2012 and is planned to be in operation the first quarter of 2015 as the world’s first FLNG vessel. The project is progressing on schedule and is expected to be completed in April 2014.

The combined capacity of the three LNG storage tanks, which were supplied by TGE, is 16,100cu m, with a net weight of approximately 395 tons each. The complete tanks were hoisted by two 400-ton goliath gantry cranes in WOM’s dry dock.

Current News

Siem Offshore Rebrands as Sea1 Offshore Following Chairman Exit

Siem Offshore Rebrands as Sea1

McDermott Performs Record-Breaking Lift on BorWin6 HVDC Project

McDermott Performs Record-Brea

Cyan Renewables, Hyundai to Set Up Offshore Wind Vessel Suply Chain in South Korea

Cyan Renewables, Hyundai to Se

SubseaPartner Lands Diving Job at Vår Energi’s Fields Offshore Norway

SubseaPartner Lands Diving Job

Subscribe for OE Digital E‑News

Offshore Engineer Magazine