Goliat FPSO living quarters lifted

Eni Norge provides this video clip of the living quarters being lifted into place at the Goliat FPSO. Lifting the modules, required the use of a crane with the capacity to lift 1.6 million kg, ENI said. The five-level living quarters modules weighed 1100 tonnes, using 85% of the crane's lifting capacity. The FPSO is under construction at Hyundai Heavy Industries' yard in South Korea. Find more about the lifting operations here: http://www.eninorge.com/en/Field-development/Goliat/Milestones/Living-quarters-are-lifted-into-place/