Mammoet installs Malampaya DCP

Mammoet installed the Malampaya Phase 3 depletion compression platform (DCP) in the West Philippine Sea for Shell Philippines Exploration, in a 48-hour operation.

The Malampaya deepwater gas-to-power project, off the coast of Northwest Palawan in Philippines, employs deepwater technology to extract natural gas, which is then transported to shallow water facilities and on to three natural gas-fired power stations.

The DCP is a self-installing platform that floats into place over its end-location after which the legs are lowered onto the prepared seabed.

Using a pre-installed jacking system, it enables the 80m legs to be jacked down and lift the platform from the water to its final position.

Mammoet was contracted for the offshore operation to lower the DCP legs and lift the platform to its final height. The DCP’s end-location is next to the Malampaya Shallow Water Production Platform (SWP) to which it will be linked by a permanent bridge, also to be installed by Mammoet.

The Malampaya Project, now in Phase 3, will help sustain the extraction of natural gas from the Palawan basin and process it in a shallow water production platform. This gas will then be transported along a 504km underwater pipeline towards the onshore gas plant and eventually to its power plant customers.

Mammoet was involved in the DCP’s construction, assisting with lifting and lowering the platform during the fabrication process. During the platform’s construction, the strand jacks were also installed to prepare for the jack down of the DCP’s legs and to raise the platform into place.

Keeping a gas platform stable out at sea, while installing the platform’s legs on the seabed and being buffeted by waves, is a delicate process. To keep the platform level, some of the strand jacks need to make upward movements, while others make downwards movements at the same time.

In other words, different strand jacks must be active simultaneously in opposite directions to buffer the upwards and downwards movement of the DCP, before the legs are positioned and the platform is raised out of the water.

To facilitate this precise calibration, part of the strand jack installation included special ‘guying valves’ and a new computer system to create a constant tension to deal with the movement of the platform on the water.

The platform is now being held in its raised position, with its 80m legs secured on the seabed, awaiting the completion of the operation to weld it in place and install the connecting link-bridge. 

Read more: Multitasking on Malampaya

Image: Malampaya Phase 3 Depletion Compression 

Current News

Marlink Upgrades Simon Møkster Shipping’s Network

Marlink Upgrades Simon Møkster

Seadrill Nets Two Drillship Commitments

Seadrill Nets Two Drillship Co

SLB OneSubsea and Subsea7 Win Contract for OKEA’s Bestla Project

SLB OneSubsea and Subsea7 Win

Jason Liu Named CEO of Wood Mackenzie

Jason Liu Named CEO of Wood Ma

Subscribe for OE Digital E‑News

Offshore Engineer Magazine