Mooring work begins at Ichthys

Mooring installation has gun at Inpex's Ichthys field in Australia's Browse Basin, the company announced on 8 May 2015.

The first of 49 foundation piles was safely deployed and driven into the seabed on Wednesday, 6 May 2015, in 250m water depth. Each pile is about 66m long and weighs 450 tonnes.

Ichthys Project Managing Director Louis Bon said that installation of the complex network of subsea infrastructure and equipment across the 800sq km Ichthys Field was progressing well.

“The mooring installation works are part of the offshore installation campaign that the Ichthys LNG Project commenced in October 2014,” Bon said.

“As part of that campaign, we are installing more than 30,000 tonnes of subsea infrastructure and equipment across the Ichthys Field so that we will be able to safely and efficiently extract gas and condensate.”

“The mooring work is being carried out specifically to prepare for the arrival of the Project’s two big offshore facilities – the central processing facility and the floating production, storage and offloading facility.”

Currently under construction in South Korea, the central processing facility (CPF) and floating production, storage and offloading (FPSO) facility, once completed, will be towed to the Ichthys Field in 2016 and moored for the life of operations – about 40 years – by 40,000 tonnes of chain secured to about 20,000 tonnes of foundation piles.

The mooring installation work scope is being led by Heerema Marine Contractors (HMC) Australia – under subcontract to the lead contractor McDermott Australia – using the deepwater construction vessel DCV Aegir.

Moorings will be installed by DCV Aegir in non-continuous phases, with piles driven first and mooring chains laid out later in the campaign.

As of May 2015, the Ichthys LNG Project had installed 47km of flowlines, more than 30 flowline sleeper structures and a 6500 tonne riser support structure (RSS) in the Ichthys Field as part of the offshore installation campaign. 

Current News

Exxon to Shut Two Platforms in Guyana for Two Weeks for Pipeline Connection

Exxon to Shut Two Platforms in

US Proposes Offshore Wind Auctions Off Oregon and Maine Coasts

US Proposes Offshore Wind Auct

OKEA Submits $570 Million Bestla Oil and Gas Plan

OKEA Submits $570 Million Best

Green Light for $3 Billion Oil Port off Texas Expected By Year-end

Green Light for $3 Billion Oil

Subscribe for OE Digital E‑News

Offshore Engineer Magazine