Gemini foundations installed in record time

Van Oord has completed the installation of the 150th foundation at the Gemini Wind Park in a record time of 3.5 months.

On the 1 of July 2015, Van Oord’s newbuild installation vessel Aeolus, together with Swire Blue Oceans Pacific Osprey, started installation and the last foundation was installed on the 17 October, one month earlier than scheduled.

On 1 of February, 2016 both vessels will return to the project, completely modified for the installation of the 150 wind turbines. They will sail from Esbjerg in Denmark, where the wind turbines are produced and stored at Siemens, directly to the Gemini Wind Park.

Read more

Doubling Dutch wind capacity

Current News

BP-Eni JV Azule Inks Deal for Namibia Offshore License

BP-Eni JV Azule Inks Deal for

NSTA Awards 31 More Licenses in Latest North Sea Oil and Gas Round

NSTA Awards 31 More Licenses i

Höegh LNG Strikes Deal to Deploy FSRU Hoegh Galleon in Egypt

Höegh LNG Strikes Deal to Depl

BW Offshore Concludes Sale of FPSO Polvo

BW Offshore Concludes Sale of

Subscribe for OE Digital E‑News

Offshore Engineer Magazine