Heerema to construct Albatros wind farm module

Heerema Fabrication Group has been awarded the procurement and construction contract of the Albatros offshore transformer module (OTM) by Siemens AG on behalf of EnBW Energy.

The 1000-tonne OTM will be part of the Albatros offshore wind farm project, which will be located in 40m of water 105km offshore the German coast in the North Sea, and approximately 100km from the East Frisian Coast near EnBW Energy’s planned Hohe See wind farm. The 39sq km wind farm will have 16 Siemens Gamesa wind turbines, each with a capacity of 7MW.

The OTM, with a transmission capacity of 116 MW, is one of the main components of the offshore grid connection. Siemens will deliver the electrical equipment, which will be placed at the topside. The electricity generated by Albatros and Hohe See could cover the electricity requirements of all private households in Munich - Germany's third largest city - and save around 1.9 million tonnes of carbon dioxide per year, Heerema said in a 27 July press statement.

Construction on the OTM is expected to begin in Q1 2018 at Heerema’s yard in Zwijndrecht, the Netherlands. Sailaway of the OTM is scheduled for 1Q 2019.

Current News

Fugro’s Self-Elevating Platform On Call for Japan’s Offshore Wind

Fugro’s Self-Elevating Platfor

Galp Seeks to Sell Stake in Namibia Oilfield After Discovery

Galp Seeks to Sell Stake in Na

Ørsted Picks Rovco for Offshore Wind O&M Work in US

Ørsted Picks Rovco for Offshor

Noble Corporation’s Drillship Seizes Africa’s Drilling Opportunities

Noble Corporation’s Drillship

Subscribe for OE Digital E‑News

Offshore Engineer Magazine