Gemini foundations installed in record time

Van Oord has completed the installation of the 150th foundation at the Gemini Wind Park in a record time of 3.5 months.

On the 1 of July 2015, Van Oord’s newbuild installation vessel Aeolus, together with Swire Blue Oceans Pacific Osprey, started installation and the last foundation was installed on the 17 October, one month earlier than scheduled.

On 1 of February, 2016 both vessels will return to the project, completely modified for the installation of the 150 wind turbines. They will sail from Esbjerg in Denmark, where the wind turbines are produced and stored at Siemens, directly to the Gemini Wind Park.

Read more

Doubling Dutch wind capacity

Current News

Beacon Offshore Energy Begins Production US at Shenandoah Field

Beacon Offshore Energy Begins

Harlyn Solutions Expands Market Scope with New Dutch Base

Harlyn Solutions Expands Marke

PTTEP Acquires Southeast Asia’s Offshore Block from Chevron’s Hess Unit for $450M

PTTEP Acquires Southeast Asia’

Valeura Energy, PTTEP Partner Up on Gulf of Thailand Blocks

Valeura Energy, PTTEP Partner

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine