The Danish Energy Agency recently awarded Dong Energy the concession to build an offshore wind farm in the Kattegat Bay at a cost of DKK10 billion. The wind farm's turbines, supplied by Siemens Wind Power, will have a capacity of 3.6MW each. To be located off the island of Anholt, the facility will have a capacity of 400MW, reckoned to be sufficient to meet 4% of Denmark's power consumption.

Tender specifications dictate that the wind farm must supply its first power by late 2012, with the entire facility commissioned and all turbines connected to the grid by the end of 2013.

Failure to meet the specifications will result in reduced tariff income and a penalty.

Dong commissioned Horns Rev 2 in the Danish North Sea in 2009 and has just inaugurated the UK's Gunfleet Sands 1+2 wind farm in the Thames Estuary. OE

Categories: Europe Renewables

Related Stories

Rosetti Marino Hooks $9.6M INEOS Deal for North Sea Gas Platform

Ørsted’s Gode Wind 3 Delivers First Power

Hollandse Kust West Beta Export Cables to Come Ashore Next Week

Current News

Jan De Nul Orders Another XL Cable Layer

Sif and Dillinger Make ‘Green Deal’ for Fully Circular Offshore Wind Monopiles

Australia's Carnarvon Energy Seeks Bids for Company or Asset Sale

Doris, Rosen and Spiecapag Team Up to Repurpose Natural Gas Pipelines for Hydrogen

Subscribe for OE Digital E‑News